This week, the porta-potty and dumpster were taken away, some dirt work was done, more touch up painting, the garage door was installed, and another child friendly hand rail was added to the exterior stairs.
Wednesday, September 29, 2010
Update #23
Dates Work Completed: 9/20-9/24/10
This week, the porta-potty and dumpster were taken away, some dirt work was done, more touch up painting, the garage door was installed, and another child friendly hand rail was added to the exterior stairs.
This week, the porta-potty and dumpster were taken away, some dirt work was done, more touch up painting, the garage door was installed, and another child friendly hand rail was added to the exterior stairs.
Monday, September 20, 2010
Update #22
Dates Work Completed: 9/13-9/17/2010
Alot of work was done this week. We were trying to get it mostly completed before the weekend because Craig's brothers were coming in for the LSU game. The laminate floors were completed, the hand rail, bathroom mirrors, towel rods, doorknobs, and blinds were installed. The driveway extension was completed on Thursday. The addition is mostly completed now except for some touch up painting, the garage door, and some dirt work.
Monday, September 13, 2010
Update #21
Dates Work Completed: 9/7-9/11/10
The trim carpenters installed the stair treads and added trim in the current keeping area downstairs where stuff was removed when the stairwell was added. The laminate floors were mostly installed on Friday and Saturday. There's just a little more to be added in the playroom and where it meets the stairs.
Thursday, September 9, 2010
Update #20
Dates Work Completed: 8/29-9/3/10
Our neighbor helped us dig up a crepe myrtle that is going to be in the way when we extend the driveway to the new garage. Electricity and the a/c were turned on so we were able to remove the plywood from the interior stair entrance. The trim work was completed around the stairs.
Our neighbor helped us dig up a crepe myrtle that is going to be in the way when we extend the driveway to the new garage. Electricity and the a/c were turned on so we were able to remove the plywood from the interior stair entrance. The trim work was completed around the stairs.
Saturday, August 28, 2010
Update #19
Dates Work Completed: 8/23-8/28/10
The painter continued to work on the cabinets this week. The plumbing hardware was installed. The electrical was completed, but due to a new code didn't pass inspection. The air conditioner condenser was added because of the new code. Hopefully all this will get turned on next week.
The painter continued to work on the cabinets this week. The plumbing hardware was installed. The electrical was completed, but due to a new code didn't pass inspection. The air conditioner condenser was added because of the new code. Hopefully all this will get turned on next week.
Monday, August 23, 2010
Update #18
Monday, August 16, 2010
Update #17
Dates Work Completed: 8/9 - 8/13/10
The painters completed their first coat inside. They'll put on the 2nd coat at the very end of the project. The bottom right picture was just too funny. It was a ladies name and phone number written on the wall. We don't know if it was a girlfriend or a client, but Craig told me to take a picture of it! That bright blue wall is the only color that Craig picked out. It's for the shop bathroom...his La Tech bathroom!
Sinks, custom shower, and tile floors are being installed this coming week. The contractor is estimating that there's 3 weeks left on the project.
The painters completed their first coat inside. They'll put on the 2nd coat at the very end of the project. The bottom right picture was just too funny. It was a ladies name and phone number written on the wall. We don't know if it was a girlfriend or a client, but Craig told me to take a picture of it! That bright blue wall is the only color that Craig picked out. It's for the shop bathroom...his La Tech bathroom!
Sinks, custom shower, and tile floors are being installed this coming week. The contractor is estimating that there's 3 weeks left on the project.
Subscribe to:
Posts (Atom)