This week, the porta-potty and dumpster were taken away, some dirt work was done, more touch up painting, the garage door was installed, and another child friendly hand rail was added to the exterior stairs.
Wednesday, September 29, 2010
Update #23
This week, the porta-potty and dumpster were taken away, some dirt work was done, more touch up painting, the garage door was installed, and another child friendly hand rail was added to the exterior stairs.
Monday, September 20, 2010
Update #22
Dates Work Completed: 9/13-9/17/2010
Alot of work was done this week. We were trying to get it mostly completed before the weekend because Craig's brothers were coming in for the LSU game. The laminate floors were completed, the hand rail, bathroom mirrors, towel rods, doorknobs, and blinds were installed. The driveway extension was completed on Thursday. The addition is mostly completed now except for some touch up painting, the garage door, and some dirt work.
Monday, September 13, 2010
Update #21
Dates Work Completed: 9/7-9/11/10
The trim carpenters installed the stair treads and added trim in the current keeping area downstairs where stuff was removed when the stairwell was added. The laminate floors were mostly installed on Friday and Saturday. There's just a little more to be added in the playroom and where it meets the stairs.
Thursday, September 9, 2010
Update #20
Our neighbor helped us dig up a crepe myrtle that is going to be in the way when we extend the driveway to the new garage. Electricity and the a/c were turned on so we were able to remove the plywood from the interior stair entrance. The trim work was completed around the stairs.
Saturday, August 28, 2010
Update #19
The painter continued to work on the cabinets this week. The plumbing hardware was installed. The electrical was completed, but due to a new code didn't pass inspection. The air conditioner condenser was added because of the new code. Hopefully all this will get turned on next week.
Monday, August 23, 2010
Update #18
Monday, August 16, 2010
Update #17
The painters completed their first coat inside. They'll put on the 2nd coat at the very end of the project. The bottom right picture was just too funny. It was a ladies name and phone number written on the wall. We don't know if it was a girlfriend or a client, but Craig told me to take a picture of it! That bright blue wall is the only color that Craig picked out. It's for the shop bathroom...his La Tech bathroom!
Sinks, custom shower, and tile floors are being installed this coming week. The contractor is estimating that there's 3 weeks left on the project.
Sunday, August 8, 2010
Update #16
The trim carpenter installed the base boards, window trim, and closet shelves. He made the shutters that will be going up on the new windows on the brick side. He also nailed down the flooring that was ripped up to fix the A/C problem. The section of our patio cover that was missing was also reinstalled. When we ordered cabinets for the upstairs, we also had a cabinet made for our existing bathroom. That was also hung this week.
Sunday, August 1, 2010
Update #15
Monday, July 26, 2010
Update #14
The cabinets were delivered and installed except for a new cabinet in the existing downstairs guest bathroom. The existing shutters and front door were repainted with a new color because we didn’t have the name of the existing paint color to paint the new shutters that will be going up. The work area was cleaned up in case TS Bonnie hit us (leftover bricks moved, scraps thrown away, porta potty cleaned out, and full dumpster was taken away and a new one was received). The interior doors, baseboards, window casings, attic stairs, and stair treads were delivered. Some of the floor was removed in the new guest bathroom and guest bedroom to try to determine a problem with the A/C in the existing guest bedroom. It was determined that there was probably a crimp in the existing line. They’re going to be adding a new vent/line from the new A/C unit to try to help cool off that room some more.
Friday, July 23, 2010
Shutters & Awning
Our existing awning was Walnut Brown Tweed.
Monday, July 19, 2010
Interior Paint Selections
- Upstairs Guest Bath - Sherwin Williams Windy Blue (SW6240 on Card #35)
- Upstairs Guest Room - Sherwin Williams Rain (SW6219 on Card #32)
- Hall Bath - Sherwin Williams Swanky Gray (SW6261 on Card #38)
- Boys Bedroom - Sherwin Williams Blissful Blue (SW6527 on Card #76)
- Garage Bath - Sherwin Williams Indigo (SW6531 on Card #76)
- Playroom - Sherwin Williams Whole Wheat (SW6121 on Card #18)
Update #13
Most of the exterior painting was completed. They still have a little trim work to complete.
Also the sheetrock work was completed.
On Saturday, PawPaw brought the backhoe over to spread out the dirt pile leftover from the catch basin work. We still need a little more dirt to level it out.
Cabinets are being installed today and the trim carpenters are supposed to come later in the week. The rest of the exterior painting should be completed today or later on in the week.
Saturday, July 10, 2010
Update #12
Friday, July 2, 2010
Update #11
Monday, June 28, 2010
Update #10
Dates Work Completed: 6/21-6/25/10
The electricians finished up their rough in work, the mechanical inspection was approved, the framers boxed up some of the AC ducts, removed the carport ceiling for insulation to be installed, and cleaned up all of the scrap lumber. Also, sand, mortar, bricks and sheetrock were delivered.
Monday, June 21, 2010
Update #9
Sunday, June 13, 2010
Update #8
Date work completed: 6/7-6/11/10
Monday the framers started & finished both set of stairs. While I was cooking breakfast, they cut out the window to start the stairs. They hung some visqueen to keep the sawdust out of the sitting room. By noon, they were finished with the interior stairs. Mr. Wes, the framing subcontractor, told Luke since he was the oldest that he got to be the 1st to try out the stairs. (The rest of us had to wait until Daddy got home that night!) After they finished for the day, they hung up a piece of plywood over the opening so that the air conditioner wouldn't be escaping to the upstairs.
The framers finished up this week hanging the rest of the siding and finishing up the underside of the interior stairs. The shingles were put on this week except for the caps. Air conditioner work was done as well as lots of plumbing including installing the shop shower and the kids/hall bath tub.
Saturday, June 12, 2010
Fans and Light Fixtures
Light Kit
Larger Bedroom Ceiling Fan
Light Kit
Bulb Glasses for Light Kits
Vanity Lights
Outdoor Stair Light
Garage Fluorescent Light
http://www.cooperlighting.com/common/brands.cfm?pg=Detail&brandName=Metalux&id=17341
http://www.cooperlighting.com/specfiles/pdf/metalux/081640_WN432_4L.pdf
Laundry Fluorescent Light
http://www.americanfluorescent.com/artifacts/LW.pdf
Sunday, June 6, 2010
Bedroom & Playroom floor selection
We decided to go with a wood laminate for the bedroom and playroom upstairs, because there will be lots of unsupervised play and overall it will be more durable than wood. We picked a color that is similar to the color of our current wood floor downstairs.
Update #7
Tuesday, the framers put up the soffet and facia on the front and driveway sides of the addition, added some more siding, and framed up around the patio side windows. Craig bought some sod to put around the catch basins.
Wednesday, the framers finished putting the soffet and facia on the backside and patio side, added more siding, hung the OSB under the carport. They also started removing stuff around the window to work on the interior stairs.
Thursday, the framers finished up the siding and started building the landing area for the exterior stairs. Unfortunately, the rain came and they had to leave early. Also with all of the rain on Friday, they were unable to come out as well.
The plumber was able to come out this week and finish up roughing in the plumbing upstairs and installing the new water heater.
Saturday some of the framing crew came out and worked some more on the exterior stairs.
This coming week the framers should finish up. They had planned to start on the interior stairs on Friday, but the rain changed their plans. It will be exciting once both sets of stairs go up. Then I can actually go upstairs and look around. Craig let Luke & Cameron go up the ladder on Saturday to look around.
Friday, June 4, 2010
Bathroom Selections
Masco AquaGlass Acrylic Tub/Shower
Lahara Two Handle Centerset Lavatory Faucet
Lahara Monitor® 17 Series Tub & Shower Trim
Vortens Vienna ELX Elongated Toilet
Pearl Gray cultured marble countertop/sink from Acoustical Specialities & Athens dark gray tile flooring
Guest Bath
Lahara Two Handle Centerset Lavatory Faucet
Lahara Monitor® 17 Series Shower Trim
Vortens Vienna ELX Elongated Toilet
Pearl gray Cultured marble countertop/sink/shower from Acoustical Specialties & Athens dark gray tile flooring
Shop Bath
Aquarius Fiberglass Shower
Mainline Centerset Faucet
Lahara Monitor® 17 Series Shower Trim
Vortens Vienna ELX Elongated Toilet
Pearl gray cultured marble countertop/sink from Acoustical Specialties