Sunday, June 13, 2010

Update #8

Date work completed:  6/7-6/11/10

Monday the framers started & finished both set of stairs. While I was cooking breakfast, they cut out the window to start the stairs. They hung some visqueen to keep the sawdust out of the sitting room. By noon, they were finished with the interior stairs. Mr. Wes, the framing subcontractor, told Luke since he was the oldest that he got to be the 1st to try out the stairs. (The rest of us had to wait until Daddy got home that night!) After they finished for the day, they hung up a piece of plywood over the opening so that the air conditioner wouldn't be escaping to the upstairs.
Photobucket

The framers finished up this week hanging the rest of the siding and finishing up the underside of the interior stairs.  The shingles were put on this week except for the caps.  Air conditioner work was done as well as lots of plumbing including installing the shop shower and the kids/hall bath tub.

Photobucket

1 comment:

  1. Looking good! What again is the carport door? Is that just a storage?

    ReplyDelete

About This Blog

To show family and friends the progress being made on our home addition project

Search This Blog

Followers

  © Free Blogger Templates 'Photoblog II' by Ourblogtemplates.com 2008

Back to TOP